No.1 Station Shops Scarborough
Project Overview
LCM Group are proud to showcase our latest completed project: No.1 Station SHops, Scarborough. This 5-week project was priced at £72,057.00. The project included the strip out of the shop and a full shop front replacement. Also requested was the nstallation of a new gas central heating boiler and provided Gas Safe Certificate.
Works Undertaken
- Satisfactory EICR
- Removal of ex tenant’s signage, shop fit out and waste
- Gutter and downpipe clean
- Full shop front replacement
- Redress lead flashing
- Decoration to new shop front
- Decoration to internal rooms upstairs and downstairs
- Screed downstairs floor
- Carpet throughout
- Installation of AC Unit
- Clean kitchen and WC block
- Clean windows
More Information
Project lead (name): Austen Mason
Project Date and time to complete: 15th June 2026 – 17th July 2026 (5-week project)
Type of construction/development: Refurbishment