DODGSON STREET
PROJECT OVERVIEW
The project works involved the construction of 7 industrial units on behalf of Rochdale Borough Council. The project works took 22 weeks to complete.
DESIGN FEATURES
- Demolition required to boundary walls
- Stripping out previous bases hard standings
- Removal of Trees and vegetation
- Service/drainage diversions were required
- CFA Piling and associated works
- Brick and blockwork
- Cladding
- Individual Solar Panels
- Concrete power float floors
- Mezzanine floors/Stair access
- Electrics
- Plumbing
- Partitioning
- Industrial roller shutter doors
- Paving and extensive car parking
- Fencing
- Ram raid security barriers and security doors installed
CLIENT FEEDBACK
“All concerned are very happy with the project and the way it has been completed. I look forward to working with LCM again.” Phil Watson – Architectural Technician
“Thanks again for providing a great finished building, please pass this on to your team.” David Hughes – Building Surveyor